The Agilent Technologies GC, GC/MS, and ALS Site Preparation Guide describes how to prepare your site for Agilent GC, GC/MS, and ALS systems.
This guide outlines space, electrical, gas, venting, and environmental requirements for installing Agilent GC, GC/MS, and ALS systems. It covers customer responsibilities and preparation steps before installation begins.
It includes dimensions and weights, power consumption, heat dissipation, exhaust venting, gas and reagent requirements, cryogenic cooling, cable and hose lengths, site LAN, and basic tools.
| 7890A GC height | 50 cm (19.2 in) |
|---|---|
| 7200 Q-TOF MS height | 133 cm (52.5 in) |
| 5975 Series MSD height | 41 cm (16 in) |
| Rear clearance | at least 25 cm (10 in) |
| GC with 7693A ALS injector space | 50 cm (19.5 in) above the GC |
Performance verification requires the use of helium carrier gas.
Allow at least 25 cm (10 in) between the back of the instrument and the wall.
Agilent provides service during the warranty period and under maintenance agreements only if the specified site requirements are met.
50 cm (19.5 in) above the GC.