The ABB WavePro-D Data Center Busway Installation and Maintenance Manual provides safety guidelines, installation steps, commissioning, and troubleshooting…
This manual covers the WavePro‑D busway system used in data‑center power distribution. It explains the product’s features, applicable standards and the documentation’s purpose for installers and maintenance personnel.
Key sections include storage and handling precautions, pre‑installation preparation, detailed installation procedures, torque specifications, insulation resistance testing, commissioning, safety notes, and a troubleshooting guide for common faults. This manual is written in Chinese.
The measured insulation resistance must be at least 20 MΩ; if it is below 0.4 MΩ or shows a large deviation, the cause must be identified and corrected before proceeding.
Connector bolts must be tightened to a torque of 35 ± 5 Nm.
Required tools include a tape measure, megohmmeter, torque wrench with socket, and hex key, among others.