Installation manual for the Seakeeper 5 Stabilizing Gyro, covering mechanical, electrical, and cooling system installation and startup procedures.
The Seakeeper 5 Gyro Installation Manual provides detailed guidance for boat builders and equipment installers to correctly install the Seakeeper 5 Stabilizing Gyro. It outlines the necessary precautions for handling the unit and provides criteria for selecting an optimal installation location to minimize acceleration loadings and ensure maintenance access.
The document details two primary mounting methods: bolt-in installation for metal structures and saddle installation for glass reinforced plastic (GRP) or fiberglass hulls. It also includes comprehensive checklists for mechanical, electrical, and cooling system setups, as well as the required supplies and tools for installation.
| Maximum Load | 13.3 KN (2987 lbs.) at each of the four mounts |
|---|---|
| Steady State Noise | 70 - 75 dB un-weighted |
| Seawater Flow Rate | 4 GPM (15 LPM) minimum and 8 GPM (30 LPM) maximum |
| Saddle Dimensions | 7.5 inch (191 mm) long by 3.38 inch (85.7 mm) deep |
It must be installed aft of amidships to minimize high acceleration loadings caused by hull/wave impacts during high-speed operation or in large waves.
The two methods are Bolt-In Installation and Saddle Installation.
The gyro must only be lifted using the supplied lifting eyes.