This document is the installation and commissioning manual for the GSK988TD series dual-channel turning center CNC system, which details the installation and commissioning of the CNC system. The document emphasizes the safety precautions for operation, including transportation and storage, unpacking and inspection, wiring, and maintenance.
This manual serves as the installation and commissioning guide for the GSK GSK988TD Series Dual-Channel Turning Center CNC System (Software Version V1.12). It covers essential topics including system layout, interface signal definitions, wiring connections, parameter configuration, and system debugging to ensure safe and effective operation.
The document provides detailed instructions on the physical installation of the CNC host and operation panels, including dimensions and grounding requirements. It further explains the definitions and connections for various interfaces such as the GSK-Link bus, spindle encoder, high-speed input, and network interfaces. The guide also includes procedures for PLC operation, system diagnostics, servo adjustments, and specific settings for multi-spindle and contour control functions. This manual is written in Chinese.
| Grounding Resistance | Not greater than 0.1Ω |
|---|---|
| Minimum Power Off Time | 1 min |
| IOL-02F Input/Output | 48 points input / 32 points output |
| IOL-02F Dimensions | 63 mm×270 mm×148 mm |
The manufacturer is responsible for the safety of the CNC system and its accessories in design and structure, while the user is responsible for safe operation after learning and training.
If power must be restored after a shutdown, there must be a separation time of at least 1 minute.
No, the neutral wire (zero wire) cannot be used to replace the ground wire.