Kohler K-706264T-FM-SHP Half Door Installation Guide

Installation guide for the Kohler K-706264T-FM-SHP 10 mm tempered glass half shower door, covering tools, steps, and safety warnings.


Kohler K-706264T-FM-SHP Half Door Installation Guide - cover page
Brand
Kohler
Category
Other
Document type
Installation Guide
Language
Chinese
Pages
3
File format
PDF
File size
2.3 MB
Published
05 October, 2026
Updated
05 October, 2026
MD5 checksum
72123DFF2F9D715EAC04C50D35C58F02

About this manual

This manual provides the necessary information to install the Kohler half‑door shower enclosure. It includes safety precautions, required tools, and preparation steps such as verifying wall squareness and ensuring a waterproof substrate before beginning installation.

The guide walks the installer through positioning the door 20 mm above the floor, aligning the hinge, marking and drilling screw holes, installing hollow‑wall anchors, and securing the lock seat with water diverter. It also notes the need for a level surface and the prohibition of cutting or drilling the tempered glass. This manual is written in Chinese.

What's inside

  • Before You Begin
  • Tools Required
  • Installation Steps
  • Safety Warnings
  • Dimensions and Clearances
  • Lock Seat Installation

Specifications

Glass thickness10 mm
Door width range550‑900 mm
Installation clearance above floor20 mm
Maximum wall squareness tolerance±3 mm per meter

Frequently asked questions

How far above the floor should the half door be installed?

The door glass should be installed 20 mm above the ground.

Can the tempered glass be cut or drilled during installation?

No, the tempered glass cannot be cut, drilled, or struck by hard objects.

What is the recommended tolerance for wall squareness?

The wall should be within ±3 mm per meter of verticality.