This manual describes the installation, start-up and maintenance of the Fleck 9000/9100/9500 series water treatment equipment.
This service manual provides detailed instructions for installing, assembling, and troubleshooting Fleck 9000/9100/9500 water treatment equipment. It covers equipment configuration, timer and valve assembly, meter installation, and regeneration programming. The manual also includes safety warnings and electrical requirements for proper operation.
Installation steps include plumbing connections, tank alignment, valve assembly, and electrical setup. Troubleshooting guidance is provided for common issues during setup and operation, including air purge procedures and timer calibration.
| Water Pressure Requirement | Minimum 25 pounds (1.7 bar) |
|---|---|
| Electrical Supply | 115 volt, 60 Hertz |
| Maximum Water Pressure | 125 psi (8.6 bar) |
| Timer Regeneration Time (1/15 RPM) | 82 minutes |
A minimum of 25 pounds (1.7 bar) of water pressure is required for regeneration valve to operate effectively.
A continuous 115 volt, 60 Hertz current supply is required.
Water pressure is not to exceed 125 psi (8.6 bar).