This guide covers the installation of ZTE ZXR10 6902/6905/6908 10-Gigabit Routers/Switches, including rack mounting, power connection, cabling, and hardware…
This manual provides comprehensive instructions for installing the ZTE ZXR10 6900 series (V2.8.01) 10-Gigabit routers/switches. It covers preparation requirements, including environmental checks and tool setup, as well as detailed procedures for mounting the main equipment in standard 19-inch racks. This manual is written in Chinese.
The front face of an entire row of cabinets must be in the same plane with an error of less than 5mm.
The cable bending radius must not be less than 100 times the cable's straight diameter.
A cable tie must be used every 80mm when placing cables on a vertical cable rack.