This manual provides installation, operation, maintenance, and warranty instructions for Arctic Industries walk-in coolers and freezers.
The document serves as a comprehensive guide for the erection and maintenance of Arctic walk-in cooler/freezer units. It details procedures for inspecting shipments, handling panels to prevent damage, and preparing the installation site by ensuring proper leveling and clearance from adjacent walls.
Key sections cover specific installation steps for floor panels, ceiling panels, wall panels, and door assemblies, including the use of cam-lock mechanisms and caulking sealants. The guide also addresses outdoor installations, diamond tread plate application, and provides instructions for completing the electrical and refrigeration contractor portions of the setup.
Panels over 12' long must be held vertically or supported in the center section with additional manpower if handled flat to prevent denting.
A minimum of 2 inches of clearance or breathing space should be allowed for air circulation and to accommodate variations in building walls.
Arctic supports the use of caulking sealant in between seams to make the unit as airtight as possible, using a 1/4" bead at a rate of about 25 linear feet per tube.