ITT Goulds Pumps Single Phase Sump, effluent and Sewage installation, Operation and Maintenance instructions.
This manual provides comprehensive instructions for the installation, operation, and maintenance of Goulds single-phase sump, effluent, and sewage pumps. It covers essential safety procedures, pre-installation checks, lifting guidelines, and piping requirements to ensure proper setup and performance.
The motor chamber should be refilled with ASTM 150 turbine oil.
Power cables should be torqued to 75 in. lbs. for #16 cables and 80 in. lbs. for all other cable assemblies.
A 3/16" (4.8mm) relief hole must be drilled in the discharge pipe.