This document describes the installation, operation and maintenance of the BOMBA TURBINA VERTICAL LL8C0024_ M.
This manual covers installation, operation, and maintenance of the LL8C0024 vertical turbine pump, Line II, Version M. It describes the pump shaft, pump body, column, and discharge lantern, and includes inspection, storage, installation sequence, lubrication, startup, disassembly, assembly, maintenance, and troubleshooting sections.
It applies to oil-lubricated and water-lubricated (self-lubricated) vertical turbine pumps. The manual also covers well verification, foundation, alignment, abrasive and gas effects, and periodic maintenance tasks such as packing replacement. This manual is written in Spanish.
| Column shaft intermediate sections | 10 ft |
|---|---|
| Column shaft end sections | 5 ft |
| Oil tank capacity | 1 gallon |
| Discharge connection | Standard ASA 125 flange |
| Discharge lantern mounting | NEMA standard base |
It is designed for deep wells, cisterns, or as a pressure booster in a barrel.
It covers oil-lubricated and water-lubricated (self-lubricated) vertical turbine pumps.
Well diameter, depth, and verticality must be verified.
At least once per week.