This document is a guide to duct access for other operators implementing duct access.
This open eir document (version 2.0, May 2019) gives guidance to operators implementing duct access at the ingress and egress locations where operator chambers are interconnected with open eir chambers. It is meant to be read together with the wholesale regulated Duct Access product documentation, namely the Product Description, IPM and Technical & Operational Manual.
The document sets out the responsibilities of the operator: compliance with the Technical & Operational Manual, trained operatives and safety checks, advance notice to open eir, agreement of the access hole location with an open eir PQO before core drilling, limits on hole size, and sealing of gaps, ducts and sub-ducts with approved products. It also covers mid-point blows, the use of open eir underground utility boxes (UUB) for operator closures with their dimensions, and an appendix listing approved sealing materials, FTTx push-fit connectors and tubing suppliers.
| Interconnecting duct size | 50 mm duct sufficient for single or three-way 14/10 mm sub-duct |
|---|---|
| Minimum access hole clearance from inside corner | 50 mm |
| Moderate size closure for JB4 | L 385 mm, W 310 mm, D 100 mm |
| JB 4A joint box dimensions | 910 mm long, 890 mm wide, depth 610-1000 mm |
| Duct seal for 50 mm inner diameter | TDUX-60 |
| Duct seal for 95 mm inner diameter | TDUX-100 |
| Flexible tubing inner diameter | 28 mm |
A 50 mm duct is sufficient for applications requiring single or three-way 14/10 mm sub-duct.
An open eir PQO agrees the location of the access hole before the operative core drills it in the open eir chamber.
No. Closures cannot be accommodated in JB1, JB2 and JB5 UUBs.
Any gap between the operator duct and the chamber wall is sealed with a concrete mix.