Hoymiles Microinverter Quick Installation Guide, introduces the installation steps of Hoymiles microinverters, including planning and installing microinverters, planning and laying AC cables, etc.
This guide covers planning and mounting Hoymiles HMS-1600/1800/2000-4T microinverters, preparing and laying the AC bus cable, and completing AC connections. It also describes making an installation map, connecting PV modules, powering on the system, and setting up monitoring.
The guide lists accessories such as the AC bus, T-joints, and protection caps, and gives torque values for M8 screws, AC bus nuts, and locking screws. It notes that the photovoltaic system starts generating about two minutes after the main AC breaker is closed. This manual is written in Chinese.
| M8 screw installation torque | 9 N·m |
|---|---|
| AC bus nut tightening torque | 4.0±0.5 N·m |
| Locking screw torque | 0.4±0.1 N·m |
The M8 screw installation torque should be 9 N·m, and the screws should not be overtightened.
The AC bus nut tightening torque is 4.0±0.5 N·m.
The photovoltaic system starts generating about two minutes after the main AC breaker is closed.