This manual introduces the installation and operation of ATC and ATC Orion series sputtering systems, including warnings, uncrating, cleaning and reassembly, important installation details, utility connections, and initial system power-up.
This manual provides sequential instructions for installing and operating AJA International ATC and ATC Orion Series sputtering systems. It covers essential safety warnings regarding high voltage, RF power, and cooling water, as well as procedures for uncrating, cleaning, and reassembling vacuum components. The guide details utility connections including electrical, cooling water, process gas, and mechanical pumps.
RF biasing of the substrate should be limited to 50 WATTS; 10-30 W should be more than adequate for substrates up to 6 “ diameter.
In humid environments, the incoming cooling water temperature should be elevated to 25 °C to prevent condensation.
When the turbopump is shut off, the delayed vent valve releases a specific amount of nitrogen into the side of the pump rotor.
The vacuum chamber, system frames, and grounding stud on the rear of the power distribution box must be properly grounded and at the same potential.