BYD Battery-Box Pro 2.5-10.0 High Voltage Battery Emergency Charge Method

This document describes the emergency charge method of BYD Battery-Box Pro.


BYD Battery-Box Pro 2.5-10.0 High Voltage Battery Emergency Charge Method - cover page
Brand
BYD
Category
Other
Document type
Other
Language
English
Pages
1
File format
PDF
File size
64 KB
Published
31 October, 2023
Updated
31 October, 2023
MD5 checksum
64477B78CCF39F24D60631DF7DC131E6

About this manual

This one-page document describes the emergency charge method for the BYD Battery-Box PRO 2.5-10.0 and 13.8 high voltage battery when combined with the inverter SMA Sunny Island. It states that emergency charging is only permitted when the battery voltage measured at B+ and B- is between 35 V and 48 V, and that the work must be carried out by professional and qualified electricians following the Battery-Box installation manual and the inverter manual.

The guide lists the charging current to use, the energy limit for the charge, the need to unplug all communication cables from the BMU and to plug them back afterwards, and the complete shutdown and restart of the system after a successful charge. It also notes that for an off-grid emergency charge with a generator, suitability of the generator must be checked with SMA, and gives the EFT-Systems service contact.

What's inside

  • Charging current
  • Limited energy
  • Unplug communication cables from BMU
  • Restart
  • Service contact

Specifications

Compatible battery modelsBYD Battery-Box PRO 2.5-10.0 and 13.8
Compatible inverterSMA Sunny Island
Battery voltage for emergency charge35 V - 48 V (measured at B+ and B-)
Charging current (batteries < 5 kWh)5 A
Charging current (batteries > 5 kWh)10 A
Maximum charge duration30 minutes
Maximum energy amount15% of the nominal battery capacity

Frequently asked questions

At what battery voltage is emergency charging allowed?

Emergency charging is only allowed if the battery has a voltage of 35 V to 48 V, measured at B+ and B-.

Which charging current should be used for the emergency charge?

Use 5 A for batteries below 5 kWh and 10 A for batteries above 5 kWh.

What has to be done with the communication cables during the emergency charge?

All communication cables must be unplugged from the BMU during the charge and plugged back into the BMU afterwards.

What must be done after a successful emergency charge?

The whole system must be turned off completely until all LEDs are off, and then restarted following the installation manual.