This document provides an overview of PJM interconnection process, including request types, request classification, interconnection procedures for FERC and non-FERC jurisdictional facilities etc.
This manual outlines the process for generator interconnection requests within the PJM region, covering request types, customer classifications, FERC jurisdictional procedures, and behind-the-meter generation. It includes detailed sections on study requirements, agreements, technical standards, and applicable tariffs for both small and large generation projects.
The document is intended for new service customers, existing generation owners, PJM transmission owners, and PJM staff. It references other PJM manuals and provides attachments for technical requirements, study data, and process flowcharts.
PJM Manual 14G: Generation Interconnection Requests.
July 26, 2023.
Jason Shoemaker, Manager Interconnection Projects.
Guide developers of generation projects through the planning and study phase up to the request for facility construction.