Key facts
- Manuals
- 2
- Languages
- EN
- Last added
- 2023-10-26
Featured PJM manuals

PJM 2023 Load Forecast Supplement
This document is the 2023 Load Forecast Supplement published by the PJM Resource Adequacy Planning Department. It serves as a supplement to the 2023 PJM Load Forecast report and provides details of the processes used to develop the load forecast, along with the data and assumptions used.
The supplement describes the load forecast model and non-model adjustments. It covers sector models for Residential, Commercial, and Industrial loads, weather variables, plug-in electric vehicles, behind-the-meter battery storage, and exogenous factors such as data center and peak shaving adjustments.
Covers: Introduction and Overview · Sector Models · Residential · Commercial · Industrial · Weather Variables

PJM Manual 14A New Services Request Process
PJM Manual 14A: New Services Request Process, Revision 30 (effective July 26, 2023), is prepared by the PJM Interconnection Projects Department. It guides New Services Customers through the planning and study phase of a proposed project up to the request for facility construction, and it is one of the PJM Manual 14 series family.
The manual covers the interconnection process overview and customer classifications, initiating a new service request at the queue point and deficiency reviews, PJM support for customers, the study process (feasibility, system impact and facilities studies, coordination studies with affected systems, and work papers), and a summary of the agreements tendered. Attachments add the planning process flow diagram, cost allocation procedures, a team role clarity diagram, facilities study procedure, and a revision history.
Covers: About This Manual and Applicability · New Services Requests Study Process Overview and Determining Customer Type · Initiating a New Service Request · PJM Support for New Service Customers · New Services Request Study Process · Coordination Studies between PJM and Affected Transmission Owners
Latest PJM manuals
PJM 2023 Load Forecast Supplement
Other 33 pages · 1.2 MB · ENPJM's 2023 Load Forecast Supplement explains the load forecast model, sector models, data, and assumptions used for resource adequacy planning.
PJM Manual 14A New Services Request Process
Other 82 pages · 1.4 MB · ENPJM Manual 14A, Revision 30, describes the New Services Request process: customer types, application, feasibility and impact studies, and agreements.
Questions answered in PJM manuals
What is the purpose of this document?
It serves as a supplement to the 2023 PJM Load Forecast report and provides details of the processes used to develop the load forecast and the data and assumptions used.
Which sectors does the load forecast process consider?
The load forecast process considers three sectors: Residential, Commercial, and Industrial.
Who is the intended audience for PJM Manual 14A?
New Services Customers proposing to interconnect or upgrade generation or transmission facilities, PJM Transmission Owners and other PJM Members and their staffs, and PJM staff.
What is the effective date of Revision 30?
Revision 30 has an effective date of July 26, 2023.