Surface preparation for coatings
This document provides general installation procedures for epoxy and urethane coatings manufactured by The Euclid Chemical Company. It emphasizes that contractors must consult individual product technical data sheets for specific details such as mixing ratios and coverage rates. The guide outlines essential steps for surface preparation, including cleaning, roughening concrete, and testing for moisture vapor emission rates or relative humidity before application.
New concrete and masonry must be at least 28 days old before the coating is applied.
The tensile pull-off strength should be at least 250 psi (1.7 MPa) for the surface to be considered properly prepared.
If the relative humidity is 70% or greater, a moisture mitigation system must be used before applying the coating.