Installation instructions for Tarkett SureSet Plank and Tile covering subfloor preparation, moisture testing, and installation requirements.
This document provides installation instructions for Tarkett SureSet Plank and Tile flooring. It details requirements for different subfloor types, including suspended, on-grade, and below-grade floors, and specifies the need for a 10mil polyethylene moisture vapor barrier. The guide emphasizes proper site preparation to prevent moisture and alkali transmission from the concrete substrate.
| Minimum air space for suspended floor | 18" (460mm) |
|---|---|
| Recommended moisture vapor barrier | 10mil polyethylene |
| Minimum concrete curing time | 90 days |
| Maximum moisture emission rate | 5 lbs./1,000 sq. ft./24 hours |
| Maximum internal relative humidity | 80% |
| Maximum pH reading for concrete | 9 |
| Maximum operating temperature for radiant floors | 85ºF (29.4ºC) |
A concrete slab shall be cured a minimum of 90 days, preferably 120 days before running moisture tests.
The results should be no more than 5 lbs. per 1,000 square feet per 24 hours.
No, Tarkett Inc. does not recommend installation of tile flooring over painted surfaces.
The operating temperature must not exceed 85ºF (29.4ºC).