This manual provides detailed installation instructions for Peelle three-section slide-up freight elevator doors, covering preparation, component…
This installation manual is designed for standard Peelle product components, specifically the three-section slide-up door system. It guides installers through the entire process, from initial preparation and safety checks to the final adjustments of the door mechanism and panels. The document emphasizes the importance of proper tooling, including heavy-duty drills and chain hoists, and highlights the need for a two-person team to ensure safety during the installation of heavy components like the door panels and counterweights.
The guide details the step-by-step installation of the door guide rails, starting with determining the correct vertical position relative to the building sill and car floor. It covers the identification of parts using specific Peelle part numbers, the installation of interlock devices and position encoders, and the precise alignment of the upper, middle, and lower door panels. Special attention is given to chain tensioning, gap adjustments, and the final securing of all hardware to ensure smooth operation and safety compliance. This manual is written in Chinese.
The Peelle Three-Section Slide-Up Door.
115 V (230 V if applicable).
1/2 ton [500 kg].