Loewen LiftSlide Door Installation and Site Preparation Guide

Loewen LiftSlide door installation guide covering site preparation, opening requirements, sill pans, and FASTrack system notes.


Loewen LiftSlide Door Installation and Site Preparation Guide - cover page
Brand
Loewen
Category
Other
Document type
Installation Guide
Language
English
Pages
40
File format
PDF
File size
8.9 MB
Published
17 November, 2026
Updated
17 November, 2026
MD5 checksum
918457C2D98A718D4B1B6D99635EE0B1

About this manual

Loewen LiftSlide Door Installation Guide covers installation and site preparation for Loewen LiftSlide door systems. It is written for construction professionals with proven competency installing doors for large openings, and it recommends certified installers; the text says certified installation is required to meet warranty requirements.

The guide addresses building envelope preparation, rough opening requirements, header deflection limits, sill pan installation, and the adjustable FASTrack system. It also notes that sill pans must be used in every LiftSlide installation and that installers must work from the provided drawings to prepare the opening.

What's inside

  • General Information on Install
  • Manufacturer's Notes
  • Pre-Installation Check List
  • Preparing the Opening
  • Rigid Sill Pan Installation
  • Adjustable FASTrack System
  • Interlock Drain Assembly
  • Three Panel; Jamb; 1 1/2" Flush Sill
  • 3 Panel - Raised Track with Sill Pan

Specifications

Maximum header deflection1/8 inch along the unsupported length once fully loaded
Recommended finish floor depression depth2 1/2 inches
Sill pan minimum end dam6 inches
Sill pan interior upturn leg1/2 inch
Sill pan exterior down turn leg2 inches
Sill pan optionsRigid, flexible, or liquid
Configuration shownThree panel, jamb, 1 1/2 inch flush sill

Frequently asked questions

Are Loewen LiftSlide systems required to be installed by a certified installer?

Yes. The guide states that all systems are required to be installed by a certified installer to meet warranty requirements.

What header deflection is allowed for a LiftSlide opening?

Structural headers must allow deflection no greater than 1/8 inch along the unsupported length once the header is fully loaded.

Must sill pans be used with a Loewen LiftSlide system?

Yes. Sill pans must be used in every installation of a Loewen LiftSlide system.

What should be done to wood panels before installation?

Seal and finish all panels and wood surfaces, especially the edges, before installation.