Elpro-Energo operation manual for hermetically sealed oil distribution transformers: transport, storage, installation, commissioning, maintenance and repair.
This operation manual (Dok. No. N1-EN, dated 07.07.2022) from Elpro – Energo Transformers covers transport, storage, installation, commissioning and maintenance of hermetically sealed distribution transformers. It explains that the sealed ribbed tank absorbs the volume changes of the oil, so the standard design has no conservator and no oil-level indicator, and the oil is filled at the production site so that no overpressure or under-pressure is produced.
The manual gives transport strapping and acceleration limits, storage conditions, tightening torques for MV and LV bushing connections, the steps for changing the tap, settings for monitoring and protective devices such as R.I.S. / DGPT2 / DMCR 3.0 and the two-contact thermometer, service intervals, and procedures for oil draining, filling and testing according to IEC 60296. It ends with the scope of delivery and the optional accessories.
| Minimum storage temperature | -25 °C |
|---|---|
| Maximum installation height | 1,000 m above sea level |
| Maximum ambient operating temperature | +40 °C |
| Number of transport straps per transformer | at least 4 |
| Tightening torque, bolt M 12 | 15.5 Nm |
| Tightening torque, bolt M 20 | 52.0 Nm |
| Tightening torque, connection flag screw M 16 | 110.0 Nm |
| Protective device R.I.S. / DGPT2 / DMCR 3.0, trip temperature T1 | 100 °C |
| Protective device R.I.S. / DGPT2 / DMCR 3.0, alarm temperature T2 | 80 °C |
| Protective device pressure setting P | 0.2 Bar |
| Minimum oil breakdown values | New oil 50 kV; operating oil 30 kV |
| Wheels included in delivery | 4 pcs |
Once a year the tank, bushings, drain valve and connection flag screws are checked for oil leakage and tightness; every five years the earthing connection and electrical measurements are carried out together with the revision of the transformer station.
The storage temperature must not fall below -25 °C.
No. The tap can be changed only when the transformer is not connected to the grid, and the required tap is set according to the rating plate.
Replacement is required when the oil breakdown values are lower than 30 kV, with sampling and testing done according to IEC 60296.