SWC515 PinMount™ / SWC615 PowerMount™ Weigh Module Installation Guide
This guide provides installation instructions for the Mettler Toledo SWC515 PinMount and SWC615 PowerMount weigh modules. It covers essential preparation steps, including the requirement to remove the load cell before welding and the prohibition against cutting or extending the load cell cable. The document details the necessary tools and the importance of planning the layout before beginning the installation.
| Weld pitch (between welds) | 3" / 75mm, 2" / 50 mm |
|---|---|
| Maximum level tolerance for mounting plate | 1/2° |
| Maximum plane deviation for weigh modules | 3mm (1/8") |
| Fillet weld size for 7.5-22t modules | 0.24" / 6mm |
| Fillet weld size for 90t-100t modules | 0.47" / 12mm |
| Fillet weld size for 20-50t modules | 0.32" / 8mm |
No, you must never cut or extend the load cell's cable length.
The load cell must always be removed before welding.
A regulated power supply should be used to ensure voltage stability.
The ground wire must be as close to the weld seam as possible to ensure proper grounding.