AHT underfloor heating installation manual, which introduces installation steps, precautions, electrical connection and other information
The AHT Installation Guide explains how to install the AHT amorphous electric underfloor heating system. It lists important restrictions and requirements for stacking, folding, foot traffic, floor coverings, clearances, grounding, and electrical protection.
The guide covers getting started, planning, heating mat layout, electrical connection, installation examples, a typical wiring diagram, recommended materials, and standard heating mat sizes and power. It states that all electrical connections must be completed by certified electrical personnel. This manual is written in Chinese.
| Thermostat maximum capacity | 16 A per thermostat |
|---|---|
| Heating mat power lead length | 5 m (16 in) as stated in the document |
| Recommended minimum heating mat coverage as main heat source | 65%-80% of the room floor area |
| Spacing between heating mats | about 5 cm (2 in) |
| Recommended distance from walls | 10 cm (4 in) |
| Drying time before system operation | generally 2-14 days |
When used as the main heat source, the heating mat should cover at least 65% to 80% of the room floor area.
Each thermostat has a maximum capacity of 16 A.
Multiple thermostats are needed to share the current load when a room draws more than 16 A.
Wait until the thin-set or grout is completely dry; the guide gives a general drying time of 2 to 14 days depending on the manufacturer.