This document describes the basic principles of installing your Fired Earth floor tiles.
This Fired Earth booklet outlines the basic principles of installing Fired Earth natural stone and stone mosaic floor tiles, dated February 2017. It covers internal floor substrates and preparation, finished floor levels, under floor heating, hearths and fireplaces, planning the layout, grout joints, fixing, sealing, grouting, finishing, cleaning and maintenance, plus a section on external installation.
The guide also includes reference tables for substrate preparation, Pro 50 Levelling Compound coverage, adhesive coverage, sealants and finishes, and grout joint width and coverage. It refers readers to British Standard BS 5385 for more detailed technical information and lists showroom, technical and supplier contact numbers.
| Minimum tile distance from flames or main heat source | 300 mm |
|---|---|
| Maximum floor temperature during tiling over under floor heating | 15 °C |
| Pro 50 Levelling Compound maximum depth | 50 mm |
| Norcros standard set and fast-set S1 adhesive maximum bed depth | 10 mm |
| Grout joint sizes across the floor | 3 mm – 10 mm |
| Plywood overlay for suspended timber floors with vertical movement | 18 mm WBP plywood |
| Minimum drying time for new concrete floors | 6 weeks |
New concrete floors must be allowed to dry for a minimum of 6 weeks, and if a screed is applied on top, a further 3 weeks minimum.
The majority of Fired Earth floor tiles can be used over most under floor heating systems, but the tiles must be larger than 5x5 cm, including mosaic tesserae pieces.
Joint sizes may vary from 3mm to 10mm across the floor depending on the tile sizes and pattern; Roman and Milanese Mosaics are butt jointed except in showers, where a 3mm joint is recommended.
Tiles should be kept a minimum of 300mm away from direct contact with flames or the main heat source.