DACE Ultima RT25/50 & HT18/36 Sliding Gate Operator Installation & User Manual

This is an installation manual for the RT25/50 and HT18/36 electric gate operators from Dace


DACE Ultima RT25/50 & HT18/36 Sliding Gate Operator Installation & User Manual - cover page
Brand
D.A.C.E
Category
Automation control Equipment
Document type
Installation Guide
Language
English
Pages
52
File format
PDF
File size
2.6 MB
Published
01 November, 2023
Updated
01 November, 2023
MD5 checksum
A8F32E32A969E87C672918D0EFC491C0

About this manual

This manual covers the installation, commissioning and operation of the DACE Ultima sliding gate operator in Regular Traffic (RT25/50) and High Traffic (HT18/36) versions, driven by the Tritek control board. It explains site checks, anchoring the foundation plate, mounting the rack, gearbox oiling, wiring diagrams for safety beams, locks and receivers, and the controller menu functions such as auto close, beam settings, pedestrian entry and diagnostics.

The manual also includes a service schedule, notification and warning messages, a glossary, technical specifications, and DACE's warranty and disclaimer terms. It recommends installation by an experienced gate installer and stresses safety points such as using DuraOptics Safety Beams and having mains wiring done by a qualified electrician.

What's inside

  • Specifications
  • Operator & Site Basics
  • Installing the Operator
  • Controller Basics
  • Charging Supply Options
  • Commissioning the Operator
  • Wiring Diagrams
  • Control Board Functions
  • Additional Features
  • Service Schedule

Specifications

RT25/50 speed25/50m per min
RT25/50 max gate mass500/300kg
HT18/36 speed18/36m per min
HT18/36 max gate mass600/300kg
Motor12 Volt DC Motor

Frequently asked questions

Can the Ultima RT25/50 close at 50 meters per minute without safety beams?

No. For safety reasons, the Ultima RT 25/50 will only close at the maximum speed of 50 meters per minute if safety beams are connected to the operator.

Who should connect the mains supply to the gate operator?

If you run AC directly from the building mains supply to the transformer, the wiring should be done by a qualified/registered electrician, as this is a legal requirement.

What happens if the gate strikes an object?

The operator has built-in electronic collision sensing that makes the gate stop and reopen, but the gate strikes the object first, so DuraOptics Safety Beams are recommended on all installations.

What should be checked on the gate before installing the operator?

The manual lists checks including that the rail is level, wheels and top rollers turn freely, the gate is not bent or bowed, end stops are sufficient, and the gate mass or start-up force does not exceed the specification maximum.