The document introduces AusNet Services' electricity transmission system, including transmission towers, terminal stations, conductors, electricity grid, etc.
This booklet from AusNet Services explains what transmission line easements are and what they mean for Victorian landowners and land managers. AusNet Services owns and operates the electricity transmission system in Victoria, with about 6,500 kilometres of conductors carried mostly on steel towers, linking to neighbouring states as part of the national electricity grid.
The guide covers the purpose of easements, who owns the land, typical easement widths for different line voltages, vegetation limits, underground transmission cables, and the activities that are permitted or restricted on easements. It also explains how to make an enquiry about an easement using the application form at the rear of the publication, and refers readers to a companion booklet, Your Guide to Planting Near Electricity Lines.
| Transmission voltage range | 220 kV to 500 kV |
|---|---|
| Transmission line length | 6,500 kilometres |
| Total easement area | 17,500 hectares |
| Maximum vegetation height on easements | 3 m |
| Typical easement width, 500 kV single circuit | 65 metres |
| Typical easement width, 220 kV double circuit | 40 metres |
Usually AusNet Services does not own the land; ownership remains with the landowner, who has restricted use of the easement, while AusNet Services has acquired rights for its use and statutory authority to restrict activities.
The maximum mature height of vegetation on easements is 3 metres.
Before any works involving digging, excavation, change of ground surface cover or driving of stakes or posts, a Dial Before You Dig enquiry must be made.
Complete the application form at the rear of the publication and forward it to AusNet Services Asset Management Survey and Easements; the form is also available on the AusNet Services website and can be lodged electronically.