This guide provides instructions for installing and initially treating water for your Central Boiler outdoor furnace.
This guide from Central Boiler covers the installation of a Central Boiler outdoor furnace and its connection to an existing heating system. It explains how to plan the furnace location, install supply and return lines, select and install circulation pumps, and connect to water heaters, forced-air systems, hydronic systems, boilers, baseboard heaters, radiant systems, and pools or hot tubs.
The guide also details the final installation steps, including testing supply water, checking for leaks, adding MolyArmor 350 corrosion inhibitor, filling the furnace with water, purging air, heating the system water to 185°F (85°C), and testing the treated water. It repeatedly directs readers to consult their Owner's Manual for model-specific information and to use a qualified installer in accordance with local and state codes.
| Clearance from combustibles - back | 44" (112 cm) |
|---|---|
| Clearance from combustibles - sides | 12" (30.5 cm) |
| Clearance from combustibles - front | 48" (122 cm) |
| Clearance from chimney inspection cover | 18" (46 cm) |
| Standard chimney length | 8 feet (2.4 m) |
| System water heating temperature | 185°F (85°C) |
No. The guide states the outdoor furnace is not intended or certified to be installed inside habitable space and must not be installed inside your home.
The furnace must be installed on a noncombustible surface or foundation, which may consist of concrete, crushed rock, or patio blocks; some models may be installed without a concrete foundation.
A spark arrester is recommended, particularly in dry conditions or where combustible material is near the unit, unless prohibited by local requirements.
The guide covers adding MolyArmor 350 corrosion inhibitor to the outdoor furnace system as part of the initial water treatment.