Pervious surfaces are alternative materials to traditional paving, allowing water to seep into the ground. They can be used in a wide range of residential settings, from a simple pathway or small patio up to a large driveway. Over the last few years, the market for these materials has grown. Currently, some very attractive and cost-effective options are available for small projects.
This document provides detailed guidance on installing pervious surfaces for residential applications. It covers materials, location, design, and maintenance requirements to ensure effective stormwater infiltration. Key considerations include material specifications, groundwater depth, setbacks from structures, utility proximity, tree protection, and slope limitations. The document also includes calculation examples for run-on drainage and infiltration testing to ensure proper system performance.
Installation must follow specific standards, including using certified installers for permeable interlocking concrete pavers and ensuring proper edge restraints and drainage management. Maintenance involves regular sweeping and occasional vacuuming to prevent clogging. The document is intended for contractors and homeowners planning to install pervious surfaces in residential settings.
| Pavement Material | Permeable interlocking pavers with 5-15% open area or interlocking grids with gravel fill |
|---|---|
| Bedding Layer | 2 inches of No. 8 stone |
| Reservoir Layer | 12 inches of No. 57 stone |
| Filter Layer | Filter fabric with flow rate > 125 gpm/sq. ft. and AOS equivalent to US #70 or #80 sieve |
| Observation Well | Perforated 4 to 6 inch vertical PVC pipe with lockable cap |
Groundwater depth should be 2 feet deeper than the excavation depth to prevent pollutants from reaching groundwater.
Pervious surfaces must be located at least 5 feet away from a building foundation if down-gradient, and 25 feet away if up-gradient, unless a 30 mil impermeable liner is installed.
Pervious surfaces are most effective on flat or nearly flat areas (≤5% slope), and the final installed surface must be ≤10% slope.