This manual from NNB Generation Company (SZC) Limited, document reference 100200202 Version 1.0, explains how the management processes for NNB GenCo (SZC) are to be implemented. It describes the Integrated Management System (IMS) used to ensure the company can act as an intelligent customer to design, procure, construct, commission, operate and eventually decommission Sizewell C nuclear power plant.
The document sets out the requirements the IMS satisfies, including IAEA GSR-2, BS EN ISO 9000:2015, BS EN ISO 14001:2015, BS EN ISO 45001:2018, Nuclear Site Licence Conditions and the Environmental Permitting Regulations, together with stakeholders, accountability and a table of references and definitions. It then covers the composition of the IMS across seven layers, the process framework, management, core and support processes, and an appendix of definitions and ownership roles.
The manual states that the IMS is the tool used to ensure NNB GenCo (SZC) can act as an intelligent customer to design, procure, construct, commission, operate and eventually decommission Sizewell C nuclear power plant.
The IMS satisfies and demonstrates compliance with applicable laws and regulation as well as IAEA Safety Requirements GSR-2, BS EN ISO 9000:2015, BS EN ISO 14001:2015, BS EN ISO 45001:2018, Nuclear Site Licence Conditions and Environmental Permitting Regulations.
According to the manual, the Finance Director is responsible for ensuring that the IMS is effective in meeting the business objectives.
The definitions list gives EDRMS as Electronic Documents & Records Management System.