The Weber External Wall Insulation Training Guide is a quick reference to the key stages in the installation of webertherm External Wall Insulation systems.
This Weber training guide supplements the training provided by Weber and is a quick reference to key stages in installing webertherm External Wall Insulation systems. It covers health and safety, preparation, beads, sills and trims, base bead fixing, fixings, boarding around windows, preparation for rendering and weather working.
The guide then describes application stages for webertherm XM, including basecoat, rendering, topcoat finishes and RB brick effect, and for webertherm XP, including scraped finish, light ashlar details, spray rough cast and dry dash finish. It also notes that full technical details are in Site Application Guides and on www.uk.weber.
| Minimum pull-out force per fixing | 0.75 kN |
|---|---|
| Base bead fixing centres | 700 mm |
| Box bead joining gap | 2 mm |
| Defective area threshold | 0.1 m² |
The guide says to confirm the required standard, the size of the job and suitable access, and to check that materials on site are correct for the specification and stored correctly.
They are normally fixed with the heel on the DPC line, at 700mm centres to line and level using short drill and drive pins.
Carry out a pull-out test with a minimum pull-out force of 0.75 KN per fixing.
A 2mm gap is left with box beads fully inserted into the joining clip.