This manual details the installation process of the Crystal Elevator, including site preparation, guide rails and cross braces, motors and running gear, carriage, safeties, doors, doors lock operator cams, over speed governor etc.
This manual provides step-by-step installation instructions for the RAM Crystal Elevator. It covers essential procedures including site preparation and setup, the assembly and installation of guide rails and cross braces, and the mounting of motors and running gear. The document also details the installation of the carriage, safeties, and doors, along with specific instructions for door lock operator cams and the over-speed governor.
| Minimum shaft ceiling clearance | 96 inches |
|---|---|
| Door height clearance (standard Bi-fold) | 83 inches |
| Guide rail bolt torque | 80 ft-lbs |
A minimum of 96 inches is required from the finished top floor to the shaft ceiling.
You must ensure 83 inches of door height clearance from the top of the finished floor to the door header.