Highway Surveying Construction Procedures Manual

This manual introduces the methods of surveying in highway construction.


Highway Surveying Construction Procedures Manual - cover page
Document type
User Manual
Language
English
Pages
22
File format
PDF
File size
1.4 MB
Published
15 October, 2023
Updated
15 October, 2023
MD5 checksum
E4AD508D02A28C639D6508487757E233

About this manual

This manual outlines the preparation and execution phases of construction surveying. It emphasizes the importance of studying contract plans, protecting existing monuments, and performing double-checks on all calculations and field stakes to ensure accuracy before work begins.

The document provides specific instructions for various staking operations, including clearing and grubbing limits and slope staking using manual, conventional total station, modified conventional, and GPS/RTK methods. It includes detailed procedures for determining catch points and setting offset hubs.

What's inside

  • General Construction Survey Procedures
  • Earthwork and Surfacing Stages
  • Clearing and Grubbing Staking
  • Slope Staking Methods
  • Manual Method Slope Staking
  • Conventional Total Station Method
  • Modified Conventional Method
  • GPS/RTK Method

Frequently asked questions

What is the tolerance for slope staking?

The tolerance for slope staking is 0.10 feet horizontally and vertically.

What are the five phases of construction included in this chapter?

The five phases include Earthwork and Surfacing, Drainage, Structure layout, Miscellaneous Construction, and Post Construction Surveying.