This manual introduces the methods of surveying in highway construction.
This manual outlines the preparation and execution phases of construction surveying. It emphasizes the importance of studying contract plans, protecting existing monuments, and performing double-checks on all calculations and field stakes to ensure accuracy before work begins.
The document provides specific instructions for various staking operations, including clearing and grubbing limits and slope staking using manual, conventional total station, modified conventional, and GPS/RTK methods. It includes detailed procedures for determining catch points and setting offset hubs.
The tolerance for slope staking is 0.10 feet horizontally and vertically.
The five phases include Earthwork and Surfacing, Drainage, Structure layout, Miscellaneous Construction, and Post Construction Surveying.