Jingyuan Zhongke TY-AMR Remote Water Meter Installation Operation Specifications

This document introduces the engineering installation operation specifications of the TY-AMR remote water meter and smart meter reading system from Jingyuan Zhongke Technology Co., Ltd. The document provides detailed descriptions of the installation requirements and preparation work for the water meter, as well as the two installation methods for the remote water meter.


Jingyuan Zhongke TY-AMR Remote Water Meter Installation Operation Specifications - cover page
Brand
Jingyuan Zhongke
Document type
Installation Guide
Language
Chinese
Pages
11
File format
PDF
File size
494 KB
Published
09 October, 2022
Updated
27 September, 2023
MD5 checksum
0D007CC973CF810F2F49BAAE54BFA54E

About this manual

The document provides comprehensive instructions for installing the TY-AMR remote water meters, covering site selection, material inspection, preparation of tools, and specific installation procedures for wall-mounted, vertical, and direct pit installations. It emphasizes proper piping requirements, valve placement, and signal line connections to ensure accurate metering and system reliability. This manual is written in Chinese.

What's inside

  • Construction and Installation Points
  • Installation Preparation (Materials)
  • Installation Preparation (Tools)
  • Operation Process
  • Process Regulations
  • Smart Meter Reading System Network
  • Communication Line Laying
  • Wiring Requirements

Specifications

Maximum hot water temperature110°C
Straight pipe length before meter (Screw wing)8~10 times nominal diameter
Minimum straight pipe length for other meters300mm
Maximum main bus line length1200m
Maximum number of collectors per main bus7
Maximum extension bus line length300m
Minimum communication cable cross-section0.5mm²

Frequently asked questions

What are the installation requirements for hot water meters?

The maximum operating temperature is 110°C, and a check valve should be installed after the meter to prevent backflow if located before a boiler or heat exchanger.

What is the recommended structure for RS485 bus wiring?

A hand-in-hand daisy-chain structure must be used; star or fork connections are prohibited as they reduce reliability over long distances.

Download PDF (494 KB)