JAC-9 spring isolator is a type of isolator used for installing equipment. Before installation, make sure the model and specification are correct. Installation requires 24mm and 46mm open wrenches and a claw jack. Do not remove the pressure pad from the isolator before completing the height adjustment. Fasten the isolator with foundation bolts according to the bolt-loaded holes and fix the height with a wooden panel. Place the equipment on the isolator and fasten the isolator and equipment with bolts if there are fixed holes. For height adjustment, loosen the nuts on both sides and use a 46mm open wrench to adjust the two M30 bolts counterclockwise, pressing down the spring and raising the iron sheet. Stop adjusting and remove the wooden panel once the pressure pad can be taken out. The installation is complete after removing the pressure pad.
This document provides an installation guide for the JSC Scientific Controls JAC-9 spring isolator. It outlines the necessary tools, including 24mm (M16) and 46mm (M30) open wrenches and a claw jack, required before beginning the process.
The guide details the step-by-step procedure: fastening the isolator with foundation bolts, placing equipment on top, adjusting height by loosening nuts and turning M30 adjustment bolts anti-clockwise to raise the iron sheet, and finally removing the pressure pad upon completion. It also includes maintenance checking points for mounting bolts and spring deflection.
Installation requires a 24mm open wrench, a 46mm open wrench, and a claw jack.
You must loosen the nuts on both sides for 5 to 10mm first.
The wooden panel can be removed once you are able to take out the pressure pad.