This service manual outlines installation, operation and maintenance procedures for the flanged ”G4” models of Moyno 2000 pump. It covers topics such as installation, piping, foundation, shaft alignment, start-up and shutdown, packing adjustment and replacement, lubrication, and cleaning.
About this manual
The Moyno 2000 Pump is a progressing cavity pump designed for reliable, pulsation‑free positive‑displacement flow. This service manual provides detailed information on the G4 enhanced feed models, including nameplate data, model numbering, frame and type designations, and trim codes.
It covers all aspects of installation, piping, foundation, shaft alignment, water‑flush packing, operation procedures, routine maintenance, disassembly, and parts replacement. Safety cautions, troubleshooting charts, and parts lists are included to assist service technicians in keeping the pump running efficiently.
What's inside
- Introduction
- Nameplate Data
- Pump Rotation
- Model Number Structure
- Frame Size Designation
- Type Designation
- Trim Code
- Installation
- Piping
- Foundation
Specifications
| Pump type | Progressing cavity pump |
|---|
| Normal rotation direction | Clockwise |
|---|
| Suction housing material code | C = Cast Iron |
|---|
| Drive shaft material code | D = Alloy steel |
|---|
| Stator material code | Q = Nitrile (70 Durometer) |
Frequently asked questions
What is the normal rotation direction of the Moyno 2000 pump?
Normal rotation of Moyno 2000 pumps is clockwise.
What flow rate is recommended for water flushing of the packing?
Flow rate should be approximately ½ - 2 GPM.
How should suction piping be sized for the pump?
Suction piping should be as short as possible and normally the same size as the pump suction.